#324 A Shift of Power on Europe’s Borders

#324 A Shift of Power on Europe’s Borders

Released Thursday, 10th April 2025
Good episode? Give it some love!
#324 A Shift of Power on Europe’s Borders

#324 A Shift of Power on Europe’s Borders

#324 A Shift of Power on Europe’s Borders

#324 A Shift of Power on Europe’s Borders

Thursday, 10th April 2025
Good episode? Give it some love!
Rate Episode

Episode Transcript

Transcripts are displayed as originally observed. Some content, including advertisements may have changed.

Use Ctrl + F to search

0:00

In February of this year

0:02

and with the flick of a switch, Europe's

0:05

energy systems were reshaped. Around

0:14

the world, electrical transmission operators have

0:16

been working to build a

0:18

new type of grid. These

0:20

will be ready for the

0:22

far more distributed and fluctuating

0:25

generation provided by renewables. They

0:27

must be suited to the demands of

0:29

the energy trilemma. The power should

0:31

be reliable, affordable and

0:33

sustainable. In

0:41

the Baltic states, stretching between Poland to

0:43

the south and Russia to the north, there's

0:46

been an additional driver for change. These

0:49

countries' grids have been tied since

0:51

their inception to that of their neighbour

0:53

Russia. To maintain reliability

0:55

and to ensure the power

0:57

they use is from sustainable sources,

0:59

they needed to reorient their

1:01

grids, synchronising them with those to

1:03

the West. This was a project

1:06

decades in the making. It

1:08

required the installation of new

1:10

overhead lines, new systems to

1:12

manage supply and demand, and

1:14

new international connections. It

1:16

would cost 1 .6 billion

1:18

euros and require years of

1:21

careful diplomacy. But

1:23

when the switch came, it came

1:25

in an instant. The

1:38

tension in the control

1:40

room was physically, you

1:42

felt it physically, this

1:44

kind of important moment

1:46

or second that we're

1:48

going to make history

1:50

disconnect. First, and

1:53

then one day later, to

1:55

connect to the connective

1:57

Europe, but to see visually

1:59

how the frequencies synchronized, it

2:01

was quite emotional. And

2:07

the cheers and happy faces. I've never

2:09

seen my head of control center so

2:11

happy in my life. People,

2:14

everybody was really... It was basically landing

2:16

in the moon. The feeling of

2:18

landing in the moon. It was an

2:20

excellent, excellent feeling. Latvia,

2:24

Lithuania and Estonia had achieved

2:26

their political independence with mass

2:28

protests during the fall of

2:30

the Soviet Union in the

2:32

early 1990s. For a

2:34

young Hannes Kont, now director

2:37

of the synchronization project for

2:39

Estonian transmission system operator Ellering,

2:41

this was a life -changing time. I

2:44

think my personality was

2:46

shaped by the Berlin

2:48

Wall, by the... end

2:51

of history, kind of attitude

2:53

in the end of 80s,

2:56

beginning of 90s. So I

2:58

can say that my generation,

3:00

I'm 50 now, my generation

3:02

is actually shaped totally by

3:04

the understanding that we can

3:07

tear down those walls. This

3:09

kind of emotional

3:11

understanding that sooner or

3:13

later this evil empire will

3:16

diminish and we can actually

3:18

break free from this prison. But

3:21

that optimism was tempered by an

3:23

awareness of the threat posed by

3:25

Russia. up

3:29

to this point I was clear that I

3:31

was going to study theatre. I

3:33

go into a theater school

3:35

but after that because of

3:37

this feeling that we need

3:39

to somehow protect our freedom.

3:42

I, when I graduated

3:44

high school, I went,

3:46

firstly, newly graded Estonian

3:48

Defence Academy and

3:51

chose path on

3:53

my way on

3:55

career. These

3:57

nations have now been free of occupation

3:59

and foreign control for more than

4:01

30 years. But in the

4:03

decades since their independence, they've suffered

4:05

aggression and interference. More

4:08

recently, they've witnessed cyber attacks,

4:10

undersea cable and pipeline

4:12

breaches, and mystery fires on

4:14

cargo delivered by planes

4:16

departing from their airports. And

4:22

since the end of the Cold War, there

4:24

was a major vulnerability. Their electricity

4:26

transmission systems all remained

4:28

under the control of Moscow.

4:32

Protecting these countries' energy security

4:34

and strengthening the potential frontline

4:36

of free Europe in the face

4:38

of rising global autocracy would need

4:40

the same spirit of unity

4:42

and cooperation shown in the years

4:44

of liberation. Welcome

5:00

to Engineering Matters. I'm

5:02

Bernadette Ballantyne. And I'm Jonny

5:04

Dowling. This year, over the weekend

5:06

of February 7th, the Baltic

5:08

nations cut their connection to

5:10

the Moscow -controlled electricity transmission

5:12

system and synchronised their networks to

5:14

that of their neighbour, Poland, and

5:16

from there onward to the other

5:19

nations of Europe and across the

5:21

Mediterranean to North Africa. In

5:23

this episode, we'll look at the

5:25

diplomacy, investment... and engineering

5:27

excellence needed to build resilience

5:29

on one of Europe's

5:31

most important borders. In

5:42

the 1960s, the Soviet Union was

5:44

building out its electrical grid. To

5:46

the west, communist -ruled Poland, an

5:48

independent country, had linked its grid

5:51

to that of other communist

5:53

nations. is

5:55

a member of the board of ENTSOE,

5:58

the European Grid System, and

6:00

Deputy Director of Polish

6:02

Transmission System Operator, PSE. Since

6:06

the early 60s, Polish Polish system

6:08

was a part of the Synchronous

6:10

Area, which was managed, to my

6:12

understanding, from the

6:14

dispatching centre in Prague, and

6:16

also we were connected to

6:18

the Russian system. But

6:21

the Baltic nations were, at this

6:23

point, 20 years into being subsumed

6:25

into the Soviet Union. Their

6:27

grids would be established as

6:29

part of that nation's transmission

6:32

network, known as IPS -UPS,

6:34

and they were controlled in

6:36

Moscow. Historically, when

6:38

the electrification of the

6:40

industry started, so Lithuania

6:42

was part of the

6:44

Soviet Union and all... Basically,

6:47

construction of power stations,

6:49

overhead lines was centrally

6:51

managed from Moscow. So

6:53

there was like central

6:56

planning. So all networks

6:58

were built for a

7:00

single power system. But

7:03

ultimately, when

7:05

the Baltics became independent,

7:07

we immediately started

7:09

to think what can

7:11

be done to

7:13

disconnect our systems. But

7:15

back then, in the 90s,

7:18

there were very limited technical

7:20

capabilities to decouple such a

7:22

small system back then in

7:24

time. As

7:28

Donatas Matelones, Head of

7:30

Power Systems Operations with

7:32

Lithuanian TSO Litgrid explains,

7:35

his country had been selected in

7:37

the 1970s as home to one

7:39

of the Soviet Union's largest and

7:42

most modern nuclear power stations. One

7:44

unit at the Ignalina plant

7:46

was brought into operation in

7:48

1983. A second unit's

7:50

commissioning was delayed after the

7:52

Chernobyl disaster, but it came

7:54

online a year later. Together,

7:56

they met 70 % of

7:59

Lithuania's energy demand. After

8:01

independence, the EU

8:03

demanded the closure of the

8:05

plant as a condition of

8:07

EU entry and helped fund

8:09

its decommissioning. That turned Lithuania

8:11

from an energy exporter to

8:13

an energy importer reliant on

8:15

Russia for power. After

8:19

the closure of

8:21

nuclear both Lithuania but

8:23

also Baltic region

8:26

as a whole became

8:28

a deficit area

8:30

where the biggest source

8:32

of electricity came

8:34

from Russia and we

8:36

had no other

8:38

possibilities to import. After

8:40

that, there were

8:43

cables built with

8:45

Sweden, Lithuania, Poland,

8:47

and also increased

8:50

capacity between Estonia

8:52

and Finland to

8:54

diversify these import

8:56

capabilities, but also

8:59

integrating EU markets.

9:03

EU energy was not

9:05

competitive, so there were

9:07

huge imports. from

9:09

Russia. So in

9:11

Lithuania back then, if

9:13

we imported 60 % of

9:16

local consumption, so majority

9:18

of that came from

9:20

Russia. For

9:22

a while, in the

9:24

1990s and early 2000s, it

9:27

looked like freedom and

9:29

democracy might bloom in Russia.

9:31

In 2001, Belarus, Russia,

9:33

Estonia, Latvia and Lithuania agreed

9:36

to maintain the IPS -UPS

9:38

network. Under the

9:40

BREL agreement, named for these five

9:42

nations, their grids would remain

9:44

synchronized for the next 25 years.

9:47

Nominally, this system would be

9:50

managed together, but in reality,

9:52

all the levers of control

9:54

were held by Russian hands.

9:56

The frequency management was

9:58

managed by the BREL parties,

10:00

mainly Russia. So that was

10:03

a strategic risk for us.

10:05

And obviously we saw it

10:07

already after the Crimea that

10:09

we should do something

10:11

quickly to mitigate the risk. Shortly

10:14

before the Brel agreement had

10:16

been signed, KGB officer Vladimir

10:18

Putin came to power, replacing

10:21

an increasingly tired and emotional

10:23

Boris Yeltsin. Over the

10:25

years to come, Russian interference in

10:27

the political systems of its neighbors

10:29

and outright military aggression would build

10:31

and build. So in the beginning,

10:33

it was a shiny happy family.

10:36

Everybody thought that end of history, let's

10:39

join hands. And all this

10:41

emotional kind of change was

10:43

very clearly visible also within

10:45

Russia. But already

10:47

in the middle of the

10:50

90s, former Prime Minister

10:52

Primakov, who was also head

10:54

of Russian Foreign Intelligence

10:56

Service, in a closed

10:59

meeting declared. that

11:01

the emperor needs to

11:03

strike back. In 2007,

11:05

key institutions of Estonia's

11:07

economy, political system and

11:09

civil society suffered a

11:11

range of crippling cyber

11:13

attacks. That year, the

11:15

leaders of Estonia, Latvia

11:17

and Lithuania set synchronisation

11:19

with the ENTSO -E, the

11:21

European Network of Transmission

11:23

System Operators for Electricity,

11:26

as their shared strategy.

11:32

First of all, it was

11:34

important to have a

11:36

political strategic objective that, yes,

11:38

we are looking to

11:41

the solution to disconnect and

11:43

connect to European network.

11:45

And afterwards, there was a

11:47

number of studies, technical

11:50

studies, to find a technical

11:52

feasible solution to synchronize

11:54

the networks. With the Russian

11:56

invasion of eastern Ukraine

11:59

in 2014. the need

12:01

for energy security became even

12:03

more apparent to the Baltic

12:05

states. And it was obvious

12:07

for everybody, already from the,

12:09

after the 2014, they

12:11

should be, we should do

12:14

something quickly. And that's why

12:16

I was, it was very

12:18

clear that there were some

12:20

negotiations with Poland mainly. but

12:22

also with the European

12:24

Commission, how to finance and

12:27

how to manage this

12:29

major infrastructure project, because the

12:31

challenge was very, very

12:33

hard for politics. It's enormous.

12:35

As you see from

12:37

the numbers, the budget for

12:39

this program was 1 .6

12:41

billion euros. And it

12:43

was very clear from beginning

12:45

that we need to deliver. those

12:48

grid enhancements and build up of

12:50

the grid in a new system

12:52

very, very quickly. But while those

12:54

closest to Russia could see the

12:56

threat, many in Europe and

12:58

the West saw Putin as a stabilising

13:01

force. It would take a

13:03

long process of diplomacy by the

13:05

Baltic nations to persuade their neighbours of

13:07

the need to support their resilience. Still,

13:10

there was in Europe corridors

13:12

people who thought that there

13:14

is a way to doing

13:16

normal business with Russia. Let

13:19

me remind you that

13:21

Germany built Nord Stream

13:23

connections, gas connections, undersea

13:25

connection with Baltic Sea after

13:27

that. So there was

13:29

clearly tension within the

13:31

member states of EU

13:34

concerning how to face the

13:36

Russia challenge or threat.

13:39

and some member states

13:41

and some interested groups

13:43

from within the European

13:45

Commission were very sceptical

13:47

about this programme. We

13:49

should understand what it means

13:51

to synchronise two grids. It

13:56

doesn't necessarily mean that electricity

13:58

can be traded back and forth

14:00

between them, but it means

14:02

that they can be operated together,

14:04

with reserves used to keep

14:06

the entire synchronous area stable. Synchronization

14:09

is actually when the

14:11

power systems, the frequency

14:13

of the power systems

14:15

are pulsing at the

14:17

same phase. So

14:22

in Baltics and Continental

14:24

we have the same frequency,

14:27

50 Hz, but previously

14:29

they were separated. So the

14:31

control was separated and

14:33

the phase of the frequency

14:35

was separated. When we

14:37

connected synchronously, it means that,

14:39

first of all, we have

14:42

the same frequency at the

14:44

exact moment when the frequency

14:46

is high in Baltics. It

14:48

means that it's high in

14:50

continental Europe and vice versa.

14:52

And all the changes are

14:54

pulsing at the same phase.

14:58

The whole European synchronous

15:01

area, the balance control

15:03

and frequency control is

15:05

performed in a coordinated

15:07

manner. So all countries,

15:09

all areas are contributing

15:12

to the frequency. And

15:14

if there's some disturbance,

15:16

some event of outage,

15:18

or maybe there's excess

15:20

generation of renewables. it

15:23

means that all the

15:25

areas in all synchronous

15:27

area are supporting and

15:29

contributing to reduce this

15:31

failure or excess energy

15:33

so these so -called

15:35

reserves are distributed within

15:38

all synchronous area and

15:40

everybody is contributing to

15:42

to maintain the stable

15:44

and secure operation of

15:46

synchronous area before disconnecting

15:48

from ips ups the

15:50

Baltic states would need to

15:52

identify a way to connect to

15:54

ENSO -E. They could join the

15:56

system either to the main

15:58

continental Europe's synchronous area, CISA, or

16:00

to that of the Nordic

16:02

subregion. There

16:04

was a need to identify

16:07

what kind of lines we

16:09

would need to build. There

16:11

was also a discussion, maybe

16:13

the synchronization should happen with

16:15

the Nordic area. So

16:17

there were very different

16:19

discussions on a technical level.

16:23

But indeed, when the

16:25

Litpolink connection was finalised,

16:27

we established a back -to

16:29

-back connection. After completing

16:31

the studies, it was

16:34

identified that, yes, it

16:36

is the most feasible

16:38

solution to synchronise with

16:40

continental Europe. The

16:42

Litpolink is a land

16:44

connection between Lithuania and Poland.

16:46

built in 2015. It

16:48

was originally designed to trade

16:51

electricity between grids. Substantial

16:53

changes would be needed for it

16:55

to be used to synchronize frequencies on

16:57

the two grids. If the capacity

16:59

was to be used for frequency control,

17:01

then a new link would be

17:03

needed for energy trading. Poland

17:05

had been chosen as the point at which

17:07

the Baltics would connect to the wider European

17:09

system. Its grid, and that

17:11

of its former communist neighbors, had

17:13

been connected to CISA in the

17:16

1990s. To allow for

17:18

trading, with Litpol now dedicated

17:20

to frequency control, the initial

17:22

plan was to run a

17:24

subsea cable around the Russian

17:26

military enclave nestled between Lithuania

17:28

and Poland. This historically was

17:30

known as Königsberg, but it

17:32

was renamed Karlingrad in 1946

17:35

after one of Stalin's closest

17:37

allies. But

17:39

eventually the process,

17:42

the project

17:44

development... coincide

17:46

with the war

17:48

in Ukraine, the high

17:50

interest in offshore

17:53

development, and actually the

17:55

project budget exceeded

17:57

initial estimations several times.

18:00

And then the decision was found,

18:02

alternative solution was found to

18:04

implement the project on land. The

18:06

Litpol link would be used

18:08

to ensure that the grids were

18:10

kept in sync. But a

18:12

second line between the two countries,

18:14

Harmony Link is now being

18:17

built on land to allow for

18:19

trading. So now

18:21

the Harmony Link, the

18:23

interconnector between Lithuania

18:25

and Poland is now

18:27

being implemented on

18:29

land, which is

18:31

basically the objective of

18:33

this project is to

18:35

ensure a commercial exchange

18:38

possibility to import and

18:40

export electricity on both

18:42

directions. In

18:51

2018, after years of

18:53

diplomatic persuasion, the European

18:55

Commission and Poland were convinced that

18:57

synchronisation to CESA should go ahead

19:00

and funding made available. In 2019,

19:02

it was agreed that this would

19:04

be a six -year project, due

19:06

for delivery at the end of

19:08

2025. But nevertheless,

19:10

in 2018, there

19:13

was clear that in a level of

19:15

prime ministers and presidents of Baltic State

19:17

in Poland and also head of European

19:19

Commission, Janker, that there

19:21

was two agreements or

19:23

political commitments signed in

19:25

2018. And

19:28

in 2019, there was

19:30

a connection agreement Baltic States

19:32

with continental Europe system

19:34

operators. There

19:36

are three pillars to

19:38

a project like this.

19:40

physical infrastructure, IT systems

19:42

and regulatory agreements. So

19:46

first phase was to build

19:48

up infrastructure in the north

19:50

to south direction. So from

19:52

Estonia in northeast to the

19:54

Latvia, to the Lithuania, to

19:56

the Poland. So it was

19:58

enhancements or reconstruction or build

20:00

up of high -volta sewer

20:02

headlines. And then

20:04

was developing to invest

20:06

in how to

20:08

have permanent capability operating

20:10

in island mode.

20:12

So that needed some

20:14

IT investments, mainly

20:16

SCADA systems and frequency

20:18

management IT tools. So

20:21

there is a lot of different kind

20:23

of pillars, I would say. I would

20:25

say three pillars. And

20:38

the physical infrastructure

20:40

needed to allow

20:42

the Baltics to

20:45

operate their grid

20:47

outside of Moscow's

20:49

control required some

20:51

highly engineered components.

20:54

The most important for maintaining

20:56

grid stability are synchronous

20:58

condensers. In

21:02

simple terms, synchronous

21:04

condensers, it's a

21:06

rotating engine, electrical

21:08

engine, which is

21:10

rotating. And next

21:12

to the motor

21:14

is the flywheel, which

21:16

is heavy, very

21:18

heavy. And when the

21:20

rotor is spinning,

21:22

so it's... a huge

21:24

mass which is

21:26

rotating and creating inertia

21:28

on the spinning

21:30

wheel and these equipments

21:33

are necessary to

21:35

stabilize the electric power

21:37

system because in

21:39

the recent days, recent

21:41

years, when

21:43

all energy sector is

21:45

transforming to renewable

21:47

energy sources which are

21:49

intermittent. which are

21:51

converter -based. It's

21:54

power electronics used

21:56

in these equipments. In

21:59

traditional grid systems, with power

22:01

supplied by fossil fuels or

22:03

nuclear, the spinning masses at

22:06

the heart of the power

22:08

station provide inertia, keeping frequencies

22:10

steady as supply or demand

22:12

rises and falls. But

22:14

as our grid turns to renewables,

22:16

the synchronous condensers are needed to

22:18

add this inertia. As we'll see,

22:20

that means that the preparations made

22:22

in the Baltics for synchronisation also

22:24

make them highly suitable for renewable

22:26

energy. Other equipment was also needed

22:28

to connect the Baltic continental grids.

22:30

When first built in 2015, the

22:33

Litpol link had made use of

22:35

back -to -back converter stations to switch

22:37

from AC at the edge of

22:39

one grid to DC and then

22:41

back to AC at a different

22:43

voltage at the other end of

22:45

the line. This allowed

22:47

for the transfer of electricity

22:49

between grids, but it caused delays

22:51

that would prevent synchronization. With

22:53

the DC connection, you

22:56

can share the reserves, but

22:58

there is certain delay

23:00

in time in which these

23:02

reserves can be delivered.

23:05

And although there are milliseconds,

23:08

because you have the power

23:10

electronics connections, the milliseconds

23:12

in the reaction of

23:14

the back -to -back, There

23:17

is no possibility to

23:20

transfer the inertia through

23:22

the back -to -back or

23:24

DC links. That

23:29

meant a different technology. Auto

23:31

transformers would need to be

23:33

installed. These feature a

23:36

single wire, precisely wound around

23:38

itself to switch voltages. Auto

23:41

transformer is a special kind

23:43

of the transformer. And

23:46

then this device

23:48

allowed us to connect

23:50

our system but

23:52

without impact on the

23:54

frequency from one

23:56

system to the other

23:58

and without the

24:00

possibility of transferring the

24:03

phenomenon that we

24:05

would like to avoid.

24:08

The main reason why we

24:10

need that equipment is

24:12

that in due to different

24:14

voltage levels between our

24:17

networks. Continental Europe

24:19

or Polish network is

24:21

based on 400 kV

24:23

network, while Baltics

24:25

and basically all

24:27

former Soviet network was

24:30

built for 330

24:32

kV network. As

24:34

a passive component, autotransformers operate

24:36

without the millisecond lag

24:38

suffered by back -to -back AC

24:40

to DC lines. The

24:43

main feature of the synchronisation

24:45

of two systems is

24:47

ability to share, without any

24:49

delay, the reserves.

24:51

The reserves are shared with

24:53

the speed close to the

24:55

speed of light. By

24:59

2019, work on the project

25:01

was well underway. And then

25:03

the world changed. Covid

25:07

swept its way across the

25:09

planet. From airport to airport and

25:11

then from person to person.

25:14

The global pandemic had begun and

25:16

the world entered lockdown. Transportation

25:21

of the equipment was

25:23

key and we had quite

25:26

a lot of challenges

25:28

to overcome. To make it

25:30

happen that equipment would

25:32

be produced on time and

25:34

would be delivered to

25:37

the location on time. But

25:39

also it was the

25:41

cost price, cost increased

25:44

because we had to

25:46

change and find the

25:48

new suppliers to have

25:51

strategic projects finalised on

25:53

time. As

25:56

the planet learned to live with

25:59

Covid and effective vaccines were made widely

26:01

available, it looked like the project

26:03

was back on track. Russia

26:06

had invaded Ukraine in

26:08

2014. with irregular forces,

26:10

known as Little Green Men,

26:12

used to install collaborationist

26:14

regimes in the east of

26:16

the country. But on

26:18

February 21st, 2022, columns of

26:21

tanks and troops surged

26:23

over the country's borders, attempting

26:25

occupation. Ukraine's

26:27

energy assets, including the vast

26:29

Zafarisia nuclear power plant, were

26:31

targeted. The country had been

26:33

planning to move to island

26:36

operation as the extended invasion

26:38

happened, and now as CISA

26:40

for support in an emergency

26:42

synchronization. Ukrainians

26:45

were in the process

26:48

of the synchronization or

26:50

preparation for a couple

26:52

of years earlier than

26:54

the Baltics. And in

26:56

2022, in February, there

26:59

was foresaw performance

27:01

of the island operation

27:04

test. And once

27:06

the Ukrainians... disconnected

27:08

from the IPS

27:10

-UPS and went

27:13

on an island,

27:15

then the war

27:17

started. And

27:20

after the initiation

27:22

of the war,

27:24

the Ukrainians decided

27:26

not to reconnect

27:29

to the power

27:31

grid of the

27:33

aggressor and they

27:35

asked the

27:37

continental Europe for the

27:39

emergency synchronization, they

27:42

were maybe not fully

27:44

ready. They didn't

27:46

manage to deliver all

27:48

the requirements that were

27:50

supposed to, but based

27:52

on the studies that

27:54

were performed and based

27:56

on some kind of

27:58

conditions that were imposed,

28:00

we were also able

28:02

to connect them synchronously.

28:04

in March 2022 to

28:06

the continental Europe. But

28:08

the experience of Ukraine

28:10

also provided assurance. The

28:12

Baltic nations and the

28:14

rest of free Europe

28:16

had the skills and

28:18

infrastructure needed to perform

28:20

an emergency synchronization even

28:22

under wartime conditions. The

28:24

Litpol link between Lithuania and

28:26

Poland is a vital component

28:29

of the project. To prepare

28:31

for synchronization, Lithuania had pushed

28:33

hard, with European and Baltic

28:35

support, to make its own

28:37

grid ready. The Lithuanians proposed

28:39

an early test of island

28:41

operations in 2023. Island

28:44

operation, it means

28:46

that electric power systems,

28:48

Baltic power systems,

28:50

are operating in this

28:52

small island, like

28:54

a physical island in

28:56

the Mediterranean area

28:58

or, for example, an

29:00

island. which operates

29:03

synchronously with the

29:05

geographical area, but still

29:07

we can maintain

29:09

DC connections with our

29:11

neighbors because DC

29:13

converters, DC interconnections are

29:16

more or less

29:18

the same as some

29:20

offshore generator, but

29:22

such interconnectors can provide

29:24

more services, more

29:26

functionality and support the

29:29

island mode. In

29:36

the beginning, it was planned

29:38

that we're going to synchronize

29:40

in the end of 25,

29:42

in the beginning of 26.

29:44

And because of the war,

29:47

the second phase of the

29:49

war started 22 February, everybody

29:51

was clear that we need

29:53

to do it quicker and

29:55

faster. And the discussion or

29:57

diplomatic challenge was that some

29:59

parts of Lithuania was more

30:01

kind of aggressive towards this

30:03

goal. They wanted to do

30:05

it more quickly. But the

30:07

problem was that the Estonian

30:09

side, our grid was very

30:11

weak because we had already

30:13

critical parts of the grid

30:15

were not reinforced yet. While

30:18

the other Baltic nations decided they

30:20

needed more time to prepare their grids,

30:23

Lithuania went ahead with its own

30:25

test of island operation. performed

30:32

in lithuania that

30:34

was our national national

30:37

project national also

30:39

target because we set

30:41

up our lithuanian

30:43

development of power system

30:45

in such way

30:47

to have capabilities we

30:49

installed the battery

30:51

storage systems just in

30:53

order to have

30:55

technical capabilities to operate

30:57

in the island

31:00

mode and the

31:02

test was performed successfully

31:04

and that was once

31:06

again a strong basis

31:08

and strong message for

31:10

our partners that we

31:12

already have the technical

31:14

capabilities to operate in

31:16

the island mode and

31:18

also prepare for synchronization.

31:20

The invasion of Ukraine

31:22

had focused everyone's attention

31:24

on the synchronization deadline. The

31:27

Lithuanian test of its own

31:29

ability to achieve island operation and

31:31

the Polish experience of supporting

31:33

the Ukrainian emergency synchronisation had given

31:35

everyone new confidence. Now the

31:38

decision was made. Baltic synchronisation would

31:40

be brought forward by months.

31:42

Rather than taking place at the

31:44

end of 2025, it would

31:46

be scheduled for the first weekend

31:49

in February. I

31:51

would say that it's...

31:53

Ukrainian synchronization just

31:55

showed that for us

31:57

that there are

31:59

possibilities. If you are

32:01

looking to the

32:03

solutions, you can

32:05

find some and that

32:07

was an additional push

32:09

for Baltics to find

32:11

what actually is critical, what

32:14

is must and maybe some projects

32:16

could be still finalized afterwards, which

32:18

is now the case. So

32:21

that was a

32:23

discussion between partners. What

32:25

is the critical projects?

32:28

And one of these was

32:30

synchronous condensers that we

32:32

have sufficient of them to

32:34

be able to synchronize

32:36

and operate securely. The

32:38

lessons learned from Ukraine had

32:41

shown that synchronization could be performed

32:43

in an emergency, in wartime,

32:45

with a bare minimum of components.

32:48

The successful Lithuanian test of

32:50

island operation demonstrated that

32:52

these nations' networks could be

32:54

kept stable. With Russia's

32:56

aggression laid bare, CISA

32:58

supported the decision to move the

33:00

deadline forward. Around

33:04

the world, projects of this

33:06

scale routinely come in late and

33:08

over budget. Moving an international

33:10

project of this scale forward would

33:12

be unthinkable for most project

33:14

managers. It

33:16

was an enormous challenge. Anybody

33:18

who has built big

33:20

programs, created or

33:23

delivered big programs, especially

33:25

the very multinational, again,

33:27

it has to remind

33:29

that there were four

33:31

different companies from four

33:33

different countries. So it

33:35

was obviously a big

33:37

challenge to us all. to

33:40

somehow synchronize and

33:42

mitigate the risks

33:44

connecting to the

33:47

different projects. And

33:50

rescheduling the synchronization wouldn't

33:52

just require coordination between

33:54

individual private companies and

33:56

public sector operators. There

34:00

was a rigorous risk

34:02

management on this program.

34:05

It was a big, big challenge

34:07

how to... how to

34:09

have the same understanding of

34:11

the strategic risk and how

34:13

to mitigate the risk, how

34:15

to manage the risk and

34:17

how to cooperate. First of

34:19

all, it's easier to cooperate

34:22

between the business entities, but

34:24

when you engage also with

34:26

the intelligence community, because if

34:28

you want to understand what

34:30

is the Russian possible hybrid

34:32

threat against energy infrastructure. If

34:34

you want to engage also with the

34:37

ministries and agencies, it's going to be

34:39

more more complicated. This

34:41

would require a whole

34:43

-of -society approach. In

34:47

the end, everybody

34:49

came along, ministries

34:51

of energy, security services

34:53

and intelligence community, even

34:55

military stepped in in

34:57

the final days of

34:59

the synchronization. to enhance

35:01

protection of the physical

35:03

and critical infrastructure. So

35:06

at the end, that

35:08

was an enormous coordination exercise

35:10

for everybody. Still, the

35:12

threat of sabotage was clear

35:14

to everyone in the

35:16

control room. What actually made

35:18

it more complicated in

35:20

an Estonian perspective was that

35:22

the government decided that

35:25

even though the energy security

35:27

risks were mitigated, But

35:29

because just kind of

35:31

a month before there was

35:33

S -Link 2, so the

35:35

subsea cable connecting Estonia

35:38

to Scandinavia was sabotaged by

35:40

so -called Russian Shadow Fleet,

35:42

we saw that there

35:44

was a pattern. There was

35:46

a pattern that there

35:49

might be some kind of

35:51

hybrid sabotage against this

35:53

synchronization. and the government was

35:55

high alert and that's

35:57

why they decided that they

36:00

need to enhance also

36:02

a kind of civil protection

36:04

aspect of the society

36:06

and there was a kind

36:08

of nervousness in public

36:10

in general because everybody understood

36:13

that there is a

36:15

risk of blackout if Russia

36:17

is going to sabotage

36:19

this either on land or

36:21

on sea or in

36:24

cyber domain. The Baltics

36:26

would test island operation, assuring

36:28

stability across the regional

36:30

grid before connecting to CESAR.

36:32

So we had like

36:34

two days. Baltics

36:37

started to prepare

36:39

on Friday for

36:41

the test and

36:43

the synchronization. And

36:46

then for Friday

36:48

the 7th. And

36:50

then they started

36:52

to disconnect on

36:54

Sunday. the lines

36:56

with the Konigsberg

36:58

region, then Belarus,

37:00

and then remaining

37:02

elements, the remaining

37:04

lines with Russia.

37:07

And this was,

37:09

according to plan,

37:11

disconnected in the

37:13

morning on Sunday.

37:15

And simultaneously, they

37:17

ended up being on the

37:20

island. And the island

37:22

operation test was initiated. Donatus

37:32

was leading operations in

37:34

the Lithuanian control center, which

37:36

would be responsible for

37:38

coordinating synchronization with Poland and

37:40

CISA. are

38:01

planning making a calculations

38:03

that what we are operating

38:05

and what actions will

38:07

be taken so they are

38:09

secure and and will

38:12

not endanger the power systems

38:14

also we had team

38:16

of analysis analyzing the data

38:18

because during a test

38:20

we had to perform certain

38:22

tests so for example

38:24

to increase and decrease the

38:26

generation so Just

38:29

after these events, we

38:31

had to analyze the

38:33

data to draw conclusions,

38:35

whether it is correct

38:37

behavior of our control

38:39

systems, or maybe we

38:41

have to improve something. And

38:43

of course, there was

38:45

a coordination with our

38:47

partners. So there was

38:49

quite an intensive weekend

38:52

for all of us

38:54

to make it happen.

38:57

Across the Baltics, each nation

38:59

first had to disconnect

39:01

from IPS -UPS. From

39:03

the beginning, the very

39:06

important step was decoupling

39:08

from the Russian network.

39:10

So it went very

39:12

smoothly. As

39:14

planned, nine in the morning,

39:16

we were decoupled and

39:19

started the island operation. And

39:22

immediately after that, we

39:24

started the tests because

39:26

the time schedule was

39:28

quite tight. And we

39:30

performed tests which successfully

39:33

proved that our preparations

39:35

and our control systems

39:37

work fine. So

39:39

we started, in the beginning,

39:42

we started to disconnect first

39:44

from Königsberg, Kaliningrad area, Lithuania

39:47

on 8 February.

39:50

And then there was a

39:52

disconnection of lines between Lithuania

39:54

and Belarusia. Then it was

39:56

a disconnection of line between

39:58

Estonia and Russia. And then

40:00

we were island boat for

40:02

30 plus hours. So

40:05

that was the critical

40:07

that we wanted to

40:09

be separated as an

40:11

island. And why we wanted

40:13

to do it was to

40:16

test that for the future, that

40:18

we are ready for critical

40:20

scenarios, that if in future somehow

40:22

we are disconnected from continental

40:24

Europe in the context of frequency

40:26

management, that we can sustain

40:28

it and survive it with our

40:30

technology and with our power

40:32

plants. And then the engineers

40:35

spent much of the weekend stress

40:37

testing their grids in island operation.

40:41

As the tests were being conducted, a

40:44

real -life emergency happened. We

40:48

had unplanned disconnection of

40:50

one of the gas

40:52

-fired power plants. It

40:54

was not planned, but

40:56

we call it

40:59

a stress test because

41:01

it was nearly

41:03

400 megawatts of capacity

41:05

lost during island

41:07

mode. We

41:09

defined it as a

41:11

reference incident, the biggest

41:13

incident that our system

41:15

can withstand. So we

41:18

have not planned it,

41:20

but we have prepared

41:22

it. And this event

41:24

showed that all preparations

41:26

were enough and all

41:28

parameters, how our system

41:30

control is working, they

41:32

are very good. So

41:34

from one side it

41:37

was an unplanned event.

41:39

For generator it was

41:41

a failure, but for

41:43

us it was also

41:45

a success that our

41:47

work was correct. With

41:53

these planned and unplanned

41:55

stress tests passed, the control

41:58

rooms moved towards synchronization. So

42:02

eventually we had to

42:04

balance the Baltic power

42:06

system. to get

42:08

closer to the continental Europe. And

42:11

then synchronization was performed,

42:14

just connecting the circuit

42:16

breaker and connecting the

42:18

two power systems synchronously

42:20

through to transform. The

42:30

weekend was a success. Latvia,

42:32

Lithuania and Estonia had shown they

42:34

could keep their grids synchronised with

42:36

each other and with those of

42:39

their neighbours to the west. Donata

42:42

sees the successful synchronisation as

42:44

a vital step in strengthening

42:46

the Baltic's independence. First

42:50

of all, it was

42:52

the oil independence, gas independence.

42:54

We stopped electricity trade

42:56

and then we finally decoupled

42:58

our system. So first

43:00

of all, it is the

43:02

energy independence that... No

43:05

third party could have

43:07

an impact on our

43:09

energy, in this case

43:11

electricity power system, and

43:13

we ourselves are controlling

43:16

everything and we are

43:18

prepared to do it

43:20

in a secure and

43:22

cost -efficient way. It

43:25

also creates a bright future

43:27

for these nations, with modern

43:29

grids ready to export renewable

43:31

energy to partners across CISA.

43:39

Synchronization also allowed us to

43:41

create and establish the

43:43

framework for further development of

43:46

our system, that we

43:48

are developing the system on

43:50

the same parameters and

43:52

the same framework as in

43:54

the whole Europe. So

43:57

there are same rules, same

43:59

rules in the electricity

44:01

market. any

44:03

development of electricity generation

44:05

or any demand

44:07

is under the same

44:10

conditions as in

44:12

all continental Europe. And

44:15

what is important

44:17

for the decarbonization of

44:19

the energy sector,

44:21

our synchronization project, especially

44:23

with synchronous condensers,

44:26

put very good technical

44:28

conditions that we

44:30

can install. a significant

44:32

number of renewables,

44:34

which is actually happening

44:37

in Lithuania. And

44:40

it supports the stability of the

44:43

entire CESA grid. The larger the

44:45

network of power sources across the

44:47

grid, the more ability there is

44:49

to match supply and demand. So,

44:53

in a sense, there is, right now, big

44:56

discussion across Europe how...

44:58

the TSOs should be

45:00

supported and what tools

45:02

should have the TSOs.

45:04

And for us in

45:06

Poland, we are looking

45:08

forward to maintain and

45:11

expand the capacity market.

45:13

This will be also

45:15

the source of the

45:17

power for us in

45:19

case of the... loss

45:21

or not generation from

45:24

the renewables yes there

45:26

is a plan to

45:28

build additional connection what

45:30

we are right now

45:32

we are right now

45:34

in a planning phase

45:36

in designing phase of

45:39

the new connection this

45:41

will be the the

45:43

on our side this

45:45

will be 220 double

45:47

circuit 220 line and

45:49

this will be on

45:51

polish side the

45:54

cable connection. We

45:56

will build the cable

45:59

across the freeway

46:01

that we have. On

46:04

the Lithuanian side, it

46:07

will be partially cable,

46:09

partially overhead line. Currently,

46:11

the plan is to have

46:13

the new link in 2030. On,

46:17

I think, positive side, both

46:19

we and Lidric, we already

46:21

took the investment decisions and

46:23

we are like, we

46:27

are ready to perform this

46:29

project. The

46:48

engineers we've heard from today

46:50

have dedicated decades of their careers

46:52

to give their countries the

46:54

power to protect freedom's front line.

46:56

The question is, what will

46:59

today's young engineers need to do

47:01

to maintain resilience across Europe's

47:03

infrastructure? Engineering

47:17

Matters is a production of Reby

47:19

Media. This episode was written and

47:21

produced by Will North and edited

47:23

by me, Johnny Dowling. It was

47:25

hosted by me and by Bernadette

47:28

Ballantyne, sound engineering by Ross McPherson.

47:30

And the man who gives us

47:32

the capacity to operate in perfect

47:34

synchronization is Rory Harris. Thank

47:36

you for listening. You can

47:38

find us on all podcast

47:40

apps, on our website, engineeringmatters

47:43

.reby .media, and on LinkedIn. You

Unlock more with Podchaser Pro

  • Audience Insights
  • Contact Information
  • Demographics
  • Charts
  • Sponsor History
  • and More!
Pro Features