Episode Transcript
Transcripts are displayed as originally observed. Some content, including advertisements may have changed.
Use Ctrl + F to search
0:00
In February of this year
0:02
and with the flick of a switch, Europe's
0:05
energy systems were reshaped. Around
0:14
the world, electrical transmission operators have
0:16
been working to build a
0:18
new type of grid. These
0:20
will be ready for the
0:22
far more distributed and fluctuating
0:25
generation provided by renewables. They
0:27
must be suited to the demands of
0:29
the energy trilemma. The power should
0:31
be reliable, affordable and
0:33
sustainable. In
0:41
the Baltic states, stretching between Poland to
0:43
the south and Russia to the north, there's
0:46
been an additional driver for change. These
0:49
countries' grids have been tied since
0:51
their inception to that of their neighbour
0:53
Russia. To maintain reliability
0:55
and to ensure the power
0:57
they use is from sustainable sources,
0:59
they needed to reorient their
1:01
grids, synchronising them with those to
1:03
the West. This was a project
1:06
decades in the making. It
1:08
required the installation of new
1:10
overhead lines, new systems to
1:12
manage supply and demand, and
1:14
new international connections. It
1:16
would cost 1 .6 billion
1:18
euros and require years of
1:21
careful diplomacy. But
1:23
when the switch came, it came
1:25
in an instant. The
1:38
tension in the control
1:40
room was physically, you
1:42
felt it physically, this
1:44
kind of important moment
1:46
or second that we're
1:48
going to make history
1:50
disconnect. First, and
1:53
then one day later, to
1:55
connect to the connective
1:57
Europe, but to see visually
1:59
how the frequencies synchronized, it
2:01
was quite emotional. And
2:07
the cheers and happy faces. I've never
2:09
seen my head of control center so
2:11
happy in my life. People,
2:14
everybody was really... It was basically landing
2:16
in the moon. The feeling of
2:18
landing in the moon. It was an
2:20
excellent, excellent feeling. Latvia,
2:24
Lithuania and Estonia had achieved
2:26
their political independence with mass
2:28
protests during the fall of
2:30
the Soviet Union in the
2:32
early 1990s. For a
2:34
young Hannes Kont, now director
2:37
of the synchronization project for
2:39
Estonian transmission system operator Ellering,
2:41
this was a life -changing time. I
2:44
think my personality was
2:46
shaped by the Berlin
2:48
Wall, by the... end
2:51
of history, kind of attitude
2:53
in the end of 80s,
2:56
beginning of 90s. So I
2:58
can say that my generation,
3:00
I'm 50 now, my generation
3:02
is actually shaped totally by
3:04
the understanding that we can
3:07
tear down those walls. This
3:09
kind of emotional
3:11
understanding that sooner or
3:13
later this evil empire will
3:16
diminish and we can actually
3:18
break free from this prison. But
3:21
that optimism was tempered by an
3:23
awareness of the threat posed by
3:25
Russia. up
3:29
to this point I was clear that I
3:31
was going to study theatre. I
3:33
go into a theater school
3:35
but after that because of
3:37
this feeling that we need
3:39
to somehow protect our freedom.
3:42
I, when I graduated
3:44
high school, I went,
3:46
firstly, newly graded Estonian
3:48
Defence Academy and
3:51
chose path on
3:53
my way on
3:55
career. These
3:57
nations have now been free of occupation
3:59
and foreign control for more than
4:01
30 years. But in the
4:03
decades since their independence, they've suffered
4:05
aggression and interference. More
4:08
recently, they've witnessed cyber attacks,
4:10
undersea cable and pipeline
4:12
breaches, and mystery fires on
4:14
cargo delivered by planes
4:16
departing from their airports. And
4:22
since the end of the Cold War, there
4:24
was a major vulnerability. Their electricity
4:26
transmission systems all remained
4:28
under the control of Moscow.
4:32
Protecting these countries' energy security
4:34
and strengthening the potential frontline
4:36
of free Europe in the face
4:38
of rising global autocracy would need
4:40
the same spirit of unity
4:42
and cooperation shown in the years
4:44
of liberation. Welcome
5:00
to Engineering Matters. I'm
5:02
Bernadette Ballantyne. And I'm Jonny
5:04
Dowling. This year, over the weekend
5:06
of February 7th, the Baltic
5:08
nations cut their connection to
5:10
the Moscow -controlled electricity transmission
5:12
system and synchronised their networks to
5:14
that of their neighbour, Poland, and
5:16
from there onward to the other
5:19
nations of Europe and across the
5:21
Mediterranean to North Africa. In
5:23
this episode, we'll look at the
5:25
diplomacy, investment... and engineering
5:27
excellence needed to build resilience
5:29
on one of Europe's
5:31
most important borders. In
5:42
the 1960s, the Soviet Union was
5:44
building out its electrical grid. To
5:46
the west, communist -ruled Poland, an
5:48
independent country, had linked its grid
5:51
to that of other communist
5:53
nations. is
5:55
a member of the board of ENTSOE,
5:58
the European Grid System, and
6:00
Deputy Director of Polish
6:02
Transmission System Operator, PSE. Since
6:06
the early 60s, Polish Polish system
6:08
was a part of the Synchronous
6:10
Area, which was managed, to my
6:12
understanding, from the
6:14
dispatching centre in Prague, and
6:16
also we were connected to
6:18
the Russian system. But
6:21
the Baltic nations were, at this
6:23
point, 20 years into being subsumed
6:25
into the Soviet Union. Their
6:27
grids would be established as
6:29
part of that nation's transmission
6:32
network, known as IPS -UPS,
6:34
and they were controlled in
6:36
Moscow. Historically, when
6:38
the electrification of the
6:40
industry started, so Lithuania
6:42
was part of the
6:44
Soviet Union and all... Basically,
6:47
construction of power stations,
6:49
overhead lines was centrally
6:51
managed from Moscow. So
6:53
there was like central
6:56
planning. So all networks
6:58
were built for a
7:00
single power system. But
7:03
ultimately, when
7:05
the Baltics became independent,
7:07
we immediately started
7:09
to think what can
7:11
be done to
7:13
disconnect our systems. But
7:15
back then, in the 90s,
7:18
there were very limited technical
7:20
capabilities to decouple such a
7:22
small system back then in
7:24
time. As
7:28
Donatas Matelones, Head of
7:30
Power Systems Operations with
7:32
Lithuanian TSO Litgrid explains,
7:35
his country had been selected in
7:37
the 1970s as home to one
7:39
of the Soviet Union's largest and
7:42
most modern nuclear power stations. One
7:44
unit at the Ignalina plant
7:46
was brought into operation in
7:48
1983. A second unit's
7:50
commissioning was delayed after the
7:52
Chernobyl disaster, but it came
7:54
online a year later. Together,
7:56
they met 70 % of
7:59
Lithuania's energy demand. After
8:01
independence, the EU
8:03
demanded the closure of the
8:05
plant as a condition of
8:07
EU entry and helped fund
8:09
its decommissioning. That turned Lithuania
8:11
from an energy exporter to
8:13
an energy importer reliant on
8:15
Russia for power. After
8:19
the closure of
8:21
nuclear both Lithuania but
8:23
also Baltic region
8:26
as a whole became
8:28
a deficit area
8:30
where the biggest source
8:32
of electricity came
8:34
from Russia and we
8:36
had no other
8:38
possibilities to import. After
8:40
that, there were
8:43
cables built with
8:45
Sweden, Lithuania, Poland,
8:47
and also increased
8:50
capacity between Estonia
8:52
and Finland to
8:54
diversify these import
8:56
capabilities, but also
8:59
integrating EU markets.
9:03
EU energy was not
9:05
competitive, so there were
9:07
huge imports. from
9:09
Russia. So in
9:11
Lithuania back then, if
9:13
we imported 60 % of
9:16
local consumption, so majority
9:18
of that came from
9:20
Russia. For
9:22
a while, in the
9:24
1990s and early 2000s, it
9:27
looked like freedom and
9:29
democracy might bloom in Russia.
9:31
In 2001, Belarus, Russia,
9:33
Estonia, Latvia and Lithuania agreed
9:36
to maintain the IPS -UPS
9:38
network. Under the
9:40
BREL agreement, named for these five
9:42
nations, their grids would remain
9:44
synchronized for the next 25 years.
9:47
Nominally, this system would be
9:50
managed together, but in reality,
9:52
all the levers of control
9:54
were held by Russian hands.
9:56
The frequency management was
9:58
managed by the BREL parties,
10:00
mainly Russia. So that was
10:03
a strategic risk for us.
10:05
And obviously we saw it
10:07
already after the Crimea that
10:09
we should do something
10:11
quickly to mitigate the risk. Shortly
10:14
before the Brel agreement had
10:16
been signed, KGB officer Vladimir
10:18
Putin came to power, replacing
10:21
an increasingly tired and emotional
10:23
Boris Yeltsin. Over the
10:25
years to come, Russian interference in
10:27
the political systems of its neighbors
10:29
and outright military aggression would build
10:31
and build. So in the beginning,
10:33
it was a shiny happy family.
10:36
Everybody thought that end of history, let's
10:39
join hands. And all this
10:41
emotional kind of change was
10:43
very clearly visible also within
10:45
Russia. But already
10:47
in the middle of the
10:50
90s, former Prime Minister
10:52
Primakov, who was also head
10:54
of Russian Foreign Intelligence
10:56
Service, in a closed
10:59
meeting declared. that
11:01
the emperor needs to
11:03
strike back. In 2007,
11:05
key institutions of Estonia's
11:07
economy, political system and
11:09
civil society suffered a
11:11
range of crippling cyber
11:13
attacks. That year, the
11:15
leaders of Estonia, Latvia
11:17
and Lithuania set synchronisation
11:19
with the ENTSO -E, the
11:21
European Network of Transmission
11:23
System Operators for Electricity,
11:26
as their shared strategy.
11:32
First of all, it was
11:34
important to have a
11:36
political strategic objective that, yes,
11:38
we are looking to
11:41
the solution to disconnect and
11:43
connect to European network.
11:45
And afterwards, there was a
11:47
number of studies, technical
11:50
studies, to find a technical
11:52
feasible solution to synchronize
11:54
the networks. With the Russian
11:56
invasion of eastern Ukraine
11:59
in 2014. the need
12:01
for energy security became even
12:03
more apparent to the Baltic
12:05
states. And it was obvious
12:07
for everybody, already from the,
12:09
after the 2014, they
12:11
should be, we should do
12:14
something quickly. And that's why
12:16
I was, it was very
12:18
clear that there were some
12:20
negotiations with Poland mainly. but
12:22
also with the European
12:24
Commission, how to finance and
12:27
how to manage this
12:29
major infrastructure project, because the
12:31
challenge was very, very
12:33
hard for politics. It's enormous.
12:35
As you see from
12:37
the numbers, the budget for
12:39
this program was 1 .6
12:41
billion euros. And it
12:43
was very clear from beginning
12:45
that we need to deliver. those
12:48
grid enhancements and build up of
12:50
the grid in a new system
12:52
very, very quickly. But while those
12:54
closest to Russia could see the
12:56
threat, many in Europe and
12:58
the West saw Putin as a stabilising
13:01
force. It would take a
13:03
long process of diplomacy by the
13:05
Baltic nations to persuade their neighbours of
13:07
the need to support their resilience. Still,
13:10
there was in Europe corridors
13:12
people who thought that there
13:14
is a way to doing
13:16
normal business with Russia. Let
13:19
me remind you that
13:21
Germany built Nord Stream
13:23
connections, gas connections, undersea
13:25
connection with Baltic Sea after
13:27
that. So there was
13:29
clearly tension within the
13:31
member states of EU
13:34
concerning how to face the
13:36
Russia challenge or threat.
13:39
and some member states
13:41
and some interested groups
13:43
from within the European
13:45
Commission were very sceptical
13:47
about this programme. We
13:49
should understand what it means
13:51
to synchronise two grids. It
13:56
doesn't necessarily mean that electricity
13:58
can be traded back and forth
14:00
between them, but it means
14:02
that they can be operated together,
14:04
with reserves used to keep
14:06
the entire synchronous area stable. Synchronization
14:09
is actually when the
14:11
power systems, the frequency
14:13
of the power systems
14:15
are pulsing at the
14:17
same phase. So
14:22
in Baltics and Continental
14:24
we have the same frequency,
14:27
50 Hz, but previously
14:29
they were separated. So the
14:31
control was separated and
14:33
the phase of the frequency
14:35
was separated. When we
14:37
connected synchronously, it means that,
14:39
first of all, we have
14:42
the same frequency at the
14:44
exact moment when the frequency
14:46
is high in Baltics. It
14:48
means that it's high in
14:50
continental Europe and vice versa.
14:52
And all the changes are
14:54
pulsing at the same phase.
14:58
The whole European synchronous
15:01
area, the balance control
15:03
and frequency control is
15:05
performed in a coordinated
15:07
manner. So all countries,
15:09
all areas are contributing
15:12
to the frequency. And
15:14
if there's some disturbance,
15:16
some event of outage,
15:18
or maybe there's excess
15:20
generation of renewables. it
15:23
means that all the
15:25
areas in all synchronous
15:27
area are supporting and
15:29
contributing to reduce this
15:31
failure or excess energy
15:33
so these so -called
15:35
reserves are distributed within
15:38
all synchronous area and
15:40
everybody is contributing to
15:42
to maintain the stable
15:44
and secure operation of
15:46
synchronous area before disconnecting
15:48
from ips ups the
15:50
Baltic states would need to
15:52
identify a way to connect to
15:54
ENSO -E. They could join the
15:56
system either to the main
15:58
continental Europe's synchronous area, CISA, or
16:00
to that of the Nordic
16:02
subregion. There
16:04
was a need to identify
16:07
what kind of lines we
16:09
would need to build. There
16:11
was also a discussion, maybe
16:13
the synchronization should happen with
16:15
the Nordic area. So
16:17
there were very different
16:19
discussions on a technical level.
16:23
But indeed, when the
16:25
Litpolink connection was finalised,
16:27
we established a back -to
16:29
-back connection. After completing
16:31
the studies, it was
16:34
identified that, yes, it
16:36
is the most feasible
16:38
solution to synchronise with
16:40
continental Europe. The
16:42
Litpolink is a land
16:44
connection between Lithuania and Poland.
16:46
built in 2015. It
16:48
was originally designed to trade
16:51
electricity between grids. Substantial
16:53
changes would be needed for it
16:55
to be used to synchronize frequencies on
16:57
the two grids. If the capacity
16:59
was to be used for frequency control,
17:01
then a new link would be
17:03
needed for energy trading. Poland
17:05
had been chosen as the point at which
17:07
the Baltics would connect to the wider European
17:09
system. Its grid, and that
17:11
of its former communist neighbors, had
17:13
been connected to CISA in the
17:16
1990s. To allow for
17:18
trading, with Litpol now dedicated
17:20
to frequency control, the initial
17:22
plan was to run a
17:24
subsea cable around the Russian
17:26
military enclave nestled between Lithuania
17:28
and Poland. This historically was
17:30
known as Königsberg, but it
17:32
was renamed Karlingrad in 1946
17:35
after one of Stalin's closest
17:37
allies. But
17:39
eventually the process,
17:42
the project
17:44
development... coincide
17:46
with the war
17:48
in Ukraine, the high
17:50
interest in offshore
17:53
development, and actually the
17:55
project budget exceeded
17:57
initial estimations several times.
18:00
And then the decision was found,
18:02
alternative solution was found to
18:04
implement the project on land. The
18:06
Litpol link would be used
18:08
to ensure that the grids were
18:10
kept in sync. But a
18:12
second line between the two countries,
18:14
Harmony Link is now being
18:17
built on land to allow for
18:19
trading. So now
18:21
the Harmony Link, the
18:23
interconnector between Lithuania
18:25
and Poland is now
18:27
being implemented on
18:29
land, which is
18:31
basically the objective of
18:33
this project is to
18:35
ensure a commercial exchange
18:38
possibility to import and
18:40
export electricity on both
18:42
directions. In
18:51
2018, after years of
18:53
diplomatic persuasion, the European
18:55
Commission and Poland were convinced that
18:57
synchronisation to CESA should go ahead
19:00
and funding made available. In 2019,
19:02
it was agreed that this would
19:04
be a six -year project, due
19:06
for delivery at the end of
19:08
2025. But nevertheless,
19:10
in 2018, there
19:13
was clear that in a level of
19:15
prime ministers and presidents of Baltic State
19:17
in Poland and also head of European
19:19
Commission, Janker, that there
19:21
was two agreements or
19:23
political commitments signed in
19:25
2018. And
19:28
in 2019, there was
19:30
a connection agreement Baltic States
19:32
with continental Europe system
19:34
operators. There
19:36
are three pillars to
19:38
a project like this.
19:40
physical infrastructure, IT systems
19:42
and regulatory agreements. So
19:46
first phase was to build
19:48
up infrastructure in the north
19:50
to south direction. So from
19:52
Estonia in northeast to the
19:54
Latvia, to the Lithuania, to
19:56
the Poland. So it was
19:58
enhancements or reconstruction or build
20:00
up of high -volta sewer
20:02
headlines. And then
20:04
was developing to invest
20:06
in how to
20:08
have permanent capability operating
20:10
in island mode.
20:12
So that needed some
20:14
IT investments, mainly
20:16
SCADA systems and frequency
20:18
management IT tools. So
20:21
there is a lot of different kind
20:23
of pillars, I would say. I would
20:25
say three pillars. And
20:38
the physical infrastructure
20:40
needed to allow
20:42
the Baltics to
20:45
operate their grid
20:47
outside of Moscow's
20:49
control required some
20:51
highly engineered components.
20:54
The most important for maintaining
20:56
grid stability are synchronous
20:58
condensers. In
21:02
simple terms, synchronous
21:04
condensers, it's a
21:06
rotating engine, electrical
21:08
engine, which is
21:10
rotating. And next
21:12
to the motor
21:14
is the flywheel, which
21:16
is heavy, very
21:18
heavy. And when the
21:20
rotor is spinning,
21:22
so it's... a huge
21:24
mass which is
21:26
rotating and creating inertia
21:28
on the spinning
21:30
wheel and these equipments
21:33
are necessary to
21:35
stabilize the electric power
21:37
system because in
21:39
the recent days, recent
21:41
years, when
21:43
all energy sector is
21:45
transforming to renewable
21:47
energy sources which are
21:49
intermittent. which are
21:51
converter -based. It's
21:54
power electronics used
21:56
in these equipments. In
21:59
traditional grid systems, with power
22:01
supplied by fossil fuels or
22:03
nuclear, the spinning masses at
22:06
the heart of the power
22:08
station provide inertia, keeping frequencies
22:10
steady as supply or demand
22:12
rises and falls. But
22:14
as our grid turns to renewables,
22:16
the synchronous condensers are needed to
22:18
add this inertia. As we'll see,
22:20
that means that the preparations made
22:22
in the Baltics for synchronisation also
22:24
make them highly suitable for renewable
22:26
energy. Other equipment was also needed
22:28
to connect the Baltic continental grids.
22:30
When first built in 2015, the
22:33
Litpol link had made use of
22:35
back -to -back converter stations to switch
22:37
from AC at the edge of
22:39
one grid to DC and then
22:41
back to AC at a different
22:43
voltage at the other end of
22:45
the line. This allowed
22:47
for the transfer of electricity
22:49
between grids, but it caused delays
22:51
that would prevent synchronization. With
22:53
the DC connection, you
22:56
can share the reserves, but
22:58
there is certain delay
23:00
in time in which these
23:02
reserves can be delivered.
23:05
And although there are milliseconds,
23:08
because you have the power
23:10
electronics connections, the milliseconds
23:12
in the reaction of
23:14
the back -to -back, There
23:17
is no possibility to
23:20
transfer the inertia through
23:22
the back -to -back or
23:24
DC links. That
23:29
meant a different technology. Auto
23:31
transformers would need to be
23:33
installed. These feature a
23:36
single wire, precisely wound around
23:38
itself to switch voltages. Auto
23:41
transformer is a special kind
23:43
of the transformer. And
23:46
then this device
23:48
allowed us to connect
23:50
our system but
23:52
without impact on the
23:54
frequency from one
23:56
system to the other
23:58
and without the
24:00
possibility of transferring the
24:03
phenomenon that we
24:05
would like to avoid.
24:08
The main reason why we
24:10
need that equipment is
24:12
that in due to different
24:14
voltage levels between our
24:17
networks. Continental Europe
24:19
or Polish network is
24:21
based on 400 kV
24:23
network, while Baltics
24:25
and basically all
24:27
former Soviet network was
24:30
built for 330
24:32
kV network. As
24:34
a passive component, autotransformers operate
24:36
without the millisecond lag
24:38
suffered by back -to -back AC
24:40
to DC lines. The
24:43
main feature of the synchronisation
24:45
of two systems is
24:47
ability to share, without any
24:49
delay, the reserves.
24:51
The reserves are shared with
24:53
the speed close to the
24:55
speed of light. By
24:59
2019, work on the project
25:01
was well underway. And then
25:03
the world changed. Covid
25:07
swept its way across the
25:09
planet. From airport to airport and
25:11
then from person to person.
25:14
The global pandemic had begun and
25:16
the world entered lockdown. Transportation
25:21
of the equipment was
25:23
key and we had quite
25:26
a lot of challenges
25:28
to overcome. To make it
25:30
happen that equipment would
25:32
be produced on time and
25:34
would be delivered to
25:37
the location on time. But
25:39
also it was the
25:41
cost price, cost increased
25:44
because we had to
25:46
change and find the
25:48
new suppliers to have
25:51
strategic projects finalised on
25:53
time. As
25:56
the planet learned to live with
25:59
Covid and effective vaccines were made widely
26:01
available, it looked like the project
26:03
was back on track. Russia
26:06
had invaded Ukraine in
26:08
2014. with irregular forces,
26:10
known as Little Green Men,
26:12
used to install collaborationist
26:14
regimes in the east of
26:16
the country. But on
26:18
February 21st, 2022, columns of
26:21
tanks and troops surged
26:23
over the country's borders, attempting
26:25
occupation. Ukraine's
26:27
energy assets, including the vast
26:29
Zafarisia nuclear power plant, were
26:31
targeted. The country had been
26:33
planning to move to island
26:36
operation as the extended invasion
26:38
happened, and now as CISA
26:40
for support in an emergency
26:42
synchronization. Ukrainians
26:45
were in the process
26:48
of the synchronization or
26:50
preparation for a couple
26:52
of years earlier than
26:54
the Baltics. And in
26:56
2022, in February, there
26:59
was foresaw performance
27:01
of the island operation
27:04
test. And once
27:06
the Ukrainians... disconnected
27:08
from the IPS
27:10
-UPS and went
27:13
on an island,
27:15
then the war
27:17
started. And
27:20
after the initiation
27:22
of the war,
27:24
the Ukrainians decided
27:26
not to reconnect
27:29
to the power
27:31
grid of the
27:33
aggressor and they
27:35
asked the
27:37
continental Europe for the
27:39
emergency synchronization, they
27:42
were maybe not fully
27:44
ready. They didn't
27:46
manage to deliver all
27:48
the requirements that were
27:50
supposed to, but based
27:52
on the studies that
27:54
were performed and based
27:56
on some kind of
27:58
conditions that were imposed,
28:00
we were also able
28:02
to connect them synchronously.
28:04
in March 2022 to
28:06
the continental Europe. But
28:08
the experience of Ukraine
28:10
also provided assurance. The
28:12
Baltic nations and the
28:14
rest of free Europe
28:16
had the skills and
28:18
infrastructure needed to perform
28:20
an emergency synchronization even
28:22
under wartime conditions. The
28:24
Litpol link between Lithuania and
28:26
Poland is a vital component
28:29
of the project. To prepare
28:31
for synchronization, Lithuania had pushed
28:33
hard, with European and Baltic
28:35
support, to make its own
28:37
grid ready. The Lithuanians proposed
28:39
an early test of island
28:41
operations in 2023. Island
28:44
operation, it means
28:46
that electric power systems,
28:48
Baltic power systems,
28:50
are operating in this
28:52
small island, like
28:54
a physical island in
28:56
the Mediterranean area
28:58
or, for example, an
29:00
island. which operates
29:03
synchronously with the
29:05
geographical area, but still
29:07
we can maintain
29:09
DC connections with our
29:11
neighbors because DC
29:13
converters, DC interconnections are
29:16
more or less
29:18
the same as some
29:20
offshore generator, but
29:22
such interconnectors can provide
29:24
more services, more
29:26
functionality and support the
29:29
island mode. In
29:36
the beginning, it was planned
29:38
that we're going to synchronize
29:40
in the end of 25,
29:42
in the beginning of 26.
29:44
And because of the war,
29:47
the second phase of the
29:49
war started 22 February, everybody
29:51
was clear that we need
29:53
to do it quicker and
29:55
faster. And the discussion or
29:57
diplomatic challenge was that some
29:59
parts of Lithuania was more
30:01
kind of aggressive towards this
30:03
goal. They wanted to do
30:05
it more quickly. But the
30:07
problem was that the Estonian
30:09
side, our grid was very
30:11
weak because we had already
30:13
critical parts of the grid
30:15
were not reinforced yet. While
30:18
the other Baltic nations decided they
30:20
needed more time to prepare their grids,
30:23
Lithuania went ahead with its own
30:25
test of island operation. performed
30:32
in lithuania that
30:34
was our national national
30:37
project national also
30:39
target because we set
30:41
up our lithuanian
30:43
development of power system
30:45
in such way
30:47
to have capabilities we
30:49
installed the battery
30:51
storage systems just in
30:53
order to have
30:55
technical capabilities to operate
30:57
in the island
31:00
mode and the
31:02
test was performed successfully
31:04
and that was once
31:06
again a strong basis
31:08
and strong message for
31:10
our partners that we
31:12
already have the technical
31:14
capabilities to operate in
31:16
the island mode and
31:18
also prepare for synchronization.
31:20
The invasion of Ukraine
31:22
had focused everyone's attention
31:24
on the synchronization deadline. The
31:27
Lithuanian test of its own
31:29
ability to achieve island operation and
31:31
the Polish experience of supporting
31:33
the Ukrainian emergency synchronisation had given
31:35
everyone new confidence. Now the
31:38
decision was made. Baltic synchronisation would
31:40
be brought forward by months.
31:42
Rather than taking place at the
31:44
end of 2025, it would
31:46
be scheduled for the first weekend
31:49
in February. I
31:51
would say that it's...
31:53
Ukrainian synchronization just
31:55
showed that for us
31:57
that there are
31:59
possibilities. If you are
32:01
looking to the
32:03
solutions, you can
32:05
find some and that
32:07
was an additional push
32:09
for Baltics to find
32:11
what actually is critical, what
32:14
is must and maybe some projects
32:16
could be still finalized afterwards, which
32:18
is now the case. So
32:21
that was a
32:23
discussion between partners. What
32:25
is the critical projects?
32:28
And one of these was
32:30
synchronous condensers that we
32:32
have sufficient of them to
32:34
be able to synchronize
32:36
and operate securely. The
32:38
lessons learned from Ukraine had
32:41
shown that synchronization could be performed
32:43
in an emergency, in wartime,
32:45
with a bare minimum of components.
32:48
The successful Lithuanian test of
32:50
island operation demonstrated that
32:52
these nations' networks could be
32:54
kept stable. With Russia's
32:56
aggression laid bare, CISA
32:58
supported the decision to move the
33:00
deadline forward. Around
33:04
the world, projects of this
33:06
scale routinely come in late and
33:08
over budget. Moving an international
33:10
project of this scale forward would
33:12
be unthinkable for most project
33:14
managers. It
33:16
was an enormous challenge. Anybody
33:18
who has built big
33:20
programs, created or
33:23
delivered big programs, especially
33:25
the very multinational, again,
33:27
it has to remind
33:29
that there were four
33:31
different companies from four
33:33
different countries. So it
33:35
was obviously a big
33:37
challenge to us all. to
33:40
somehow synchronize and
33:42
mitigate the risks
33:44
connecting to the
33:47
different projects. And
33:50
rescheduling the synchronization wouldn't
33:52
just require coordination between
33:54
individual private companies and
33:56
public sector operators. There
34:00
was a rigorous risk
34:02
management on this program.
34:05
It was a big, big challenge
34:07
how to... how to
34:09
have the same understanding of
34:11
the strategic risk and how
34:13
to mitigate the risk, how
34:15
to manage the risk and
34:17
how to cooperate. First of
34:19
all, it's easier to cooperate
34:22
between the business entities, but
34:24
when you engage also with
34:26
the intelligence community, because if
34:28
you want to understand what
34:30
is the Russian possible hybrid
34:32
threat against energy infrastructure. If
34:34
you want to engage also with the
34:37
ministries and agencies, it's going to be
34:39
more more complicated. This
34:41
would require a whole
34:43
-of -society approach. In
34:47
the end, everybody
34:49
came along, ministries
34:51
of energy, security services
34:53
and intelligence community, even
34:55
military stepped in in
34:57
the final days of
34:59
the synchronization. to enhance
35:01
protection of the physical
35:03
and critical infrastructure. So
35:06
at the end, that
35:08
was an enormous coordination exercise
35:10
for everybody. Still, the
35:12
threat of sabotage was clear
35:14
to everyone in the
35:16
control room. What actually made
35:18
it more complicated in
35:20
an Estonian perspective was that
35:22
the government decided that
35:25
even though the energy security
35:27
risks were mitigated, But
35:29
because just kind of
35:31
a month before there was
35:33
S -Link 2, so the
35:35
subsea cable connecting Estonia
35:38
to Scandinavia was sabotaged by
35:40
so -called Russian Shadow Fleet,
35:42
we saw that there
35:44
was a pattern. There was
35:46
a pattern that there
35:49
might be some kind of
35:51
hybrid sabotage against this
35:53
synchronization. and the government was
35:55
high alert and that's
35:57
why they decided that they
36:00
need to enhance also
36:02
a kind of civil protection
36:04
aspect of the society
36:06
and there was a kind
36:08
of nervousness in public
36:10
in general because everybody understood
36:13
that there is a
36:15
risk of blackout if Russia
36:17
is going to sabotage
36:19
this either on land or
36:21
on sea or in
36:24
cyber domain. The Baltics
36:26
would test island operation, assuring
36:28
stability across the regional
36:30
grid before connecting to CESAR.
36:32
So we had like
36:34
two days. Baltics
36:37
started to prepare
36:39
on Friday for
36:41
the test and
36:43
the synchronization. And
36:46
then for Friday
36:48
the 7th. And
36:50
then they started
36:52
to disconnect on
36:54
Sunday. the lines
36:56
with the Konigsberg
36:58
region, then Belarus,
37:00
and then remaining
37:02
elements, the remaining
37:04
lines with Russia.
37:07
And this was,
37:09
according to plan,
37:11
disconnected in the
37:13
morning on Sunday.
37:15
And simultaneously, they
37:17
ended up being on the
37:20
island. And the island
37:22
operation test was initiated. Donatus
37:32
was leading operations in
37:34
the Lithuanian control center, which
37:36
would be responsible for
37:38
coordinating synchronization with Poland and
37:40
CISA. are
38:01
planning making a calculations
38:03
that what we are operating
38:05
and what actions will
38:07
be taken so they are
38:09
secure and and will
38:12
not endanger the power systems
38:14
also we had team
38:16
of analysis analyzing the data
38:18
because during a test
38:20
we had to perform certain
38:22
tests so for example
38:24
to increase and decrease the
38:26
generation so Just
38:29
after these events, we
38:31
had to analyze the
38:33
data to draw conclusions,
38:35
whether it is correct
38:37
behavior of our control
38:39
systems, or maybe we
38:41
have to improve something. And
38:43
of course, there was
38:45
a coordination with our
38:47
partners. So there was
38:49
quite an intensive weekend
38:52
for all of us
38:54
to make it happen.
38:57
Across the Baltics, each nation
38:59
first had to disconnect
39:01
from IPS -UPS. From
39:03
the beginning, the very
39:06
important step was decoupling
39:08
from the Russian network.
39:10
So it went very
39:12
smoothly. As
39:14
planned, nine in the morning,
39:16
we were decoupled and
39:19
started the island operation. And
39:22
immediately after that, we
39:24
started the tests because
39:26
the time schedule was
39:28
quite tight. And we
39:30
performed tests which successfully
39:33
proved that our preparations
39:35
and our control systems
39:37
work fine. So
39:39
we started, in the beginning,
39:42
we started to disconnect first
39:44
from Königsberg, Kaliningrad area, Lithuania
39:47
on 8 February.
39:50
And then there was a
39:52
disconnection of lines between Lithuania
39:54
and Belarusia. Then it was
39:56
a disconnection of line between
39:58
Estonia and Russia. And then
40:00
we were island boat for
40:02
30 plus hours. So
40:05
that was the critical
40:07
that we wanted to
40:09
be separated as an
40:11
island. And why we wanted
40:13
to do it was to
40:16
test that for the future, that
40:18
we are ready for critical
40:20
scenarios, that if in future somehow
40:22
we are disconnected from continental
40:24
Europe in the context of frequency
40:26
management, that we can sustain
40:28
it and survive it with our
40:30
technology and with our power
40:32
plants. And then the engineers
40:35
spent much of the weekend stress
40:37
testing their grids in island operation.
40:41
As the tests were being conducted, a
40:44
real -life emergency happened. We
40:48
had unplanned disconnection of
40:50
one of the gas
40:52
-fired power plants. It
40:54
was not planned, but
40:56
we call it
40:59
a stress test because
41:01
it was nearly
41:03
400 megawatts of capacity
41:05
lost during island
41:07
mode. We
41:09
defined it as a
41:11
reference incident, the biggest
41:13
incident that our system
41:15
can withstand. So we
41:18
have not planned it,
41:20
but we have prepared
41:22
it. And this event
41:24
showed that all preparations
41:26
were enough and all
41:28
parameters, how our system
41:30
control is working, they
41:32
are very good. So
41:34
from one side it
41:37
was an unplanned event.
41:39
For generator it was
41:41
a failure, but for
41:43
us it was also
41:45
a success that our
41:47
work was correct. With
41:53
these planned and unplanned
41:55
stress tests passed, the control
41:58
rooms moved towards synchronization. So
42:02
eventually we had to
42:04
balance the Baltic power
42:06
system. to get
42:08
closer to the continental Europe. And
42:11
then synchronization was performed,
42:14
just connecting the circuit
42:16
breaker and connecting the
42:18
two power systems synchronously
42:20
through to transform. The
42:30
weekend was a success. Latvia,
42:32
Lithuania and Estonia had shown they
42:34
could keep their grids synchronised with
42:36
each other and with those of
42:39
their neighbours to the west. Donata
42:42
sees the successful synchronisation as
42:44
a vital step in strengthening
42:46
the Baltic's independence. First
42:50
of all, it was
42:52
the oil independence, gas independence.
42:54
We stopped electricity trade
42:56
and then we finally decoupled
42:58
our system. So first
43:00
of all, it is the
43:02
energy independence that... No
43:05
third party could have
43:07
an impact on our
43:09
energy, in this case
43:11
electricity power system, and
43:13
we ourselves are controlling
43:16
everything and we are
43:18
prepared to do it
43:20
in a secure and
43:22
cost -efficient way. It
43:25
also creates a bright future
43:27
for these nations, with modern
43:29
grids ready to export renewable
43:31
energy to partners across CISA.
43:39
Synchronization also allowed us to
43:41
create and establish the
43:43
framework for further development of
43:46
our system, that we
43:48
are developing the system on
43:50
the same parameters and
43:52
the same framework as in
43:54
the whole Europe. So
43:57
there are same rules, same
43:59
rules in the electricity
44:01
market. any
44:03
development of electricity generation
44:05
or any demand
44:07
is under the same
44:10
conditions as in
44:12
all continental Europe. And
44:15
what is important
44:17
for the decarbonization of
44:19
the energy sector,
44:21
our synchronization project, especially
44:23
with synchronous condensers,
44:26
put very good technical
44:28
conditions that we
44:30
can install. a significant
44:32
number of renewables,
44:34
which is actually happening
44:37
in Lithuania. And
44:40
it supports the stability of the
44:43
entire CESA grid. The larger the
44:45
network of power sources across the
44:47
grid, the more ability there is
44:49
to match supply and demand. So,
44:53
in a sense, there is, right now, big
44:56
discussion across Europe how...
44:58
the TSOs should be
45:00
supported and what tools
45:02
should have the TSOs.
45:04
And for us in
45:06
Poland, we are looking
45:08
forward to maintain and
45:11
expand the capacity market.
45:13
This will be also
45:15
the source of the
45:17
power for us in
45:19
case of the... loss
45:21
or not generation from
45:24
the renewables yes there
45:26
is a plan to
45:28
build additional connection what
45:30
we are right now
45:32
we are right now
45:34
in a planning phase
45:36
in designing phase of
45:39
the new connection this
45:41
will be the the
45:43
on our side this
45:45
will be 220 double
45:47
circuit 220 line and
45:49
this will be on
45:51
polish side the
45:54
cable connection. We
45:56
will build the cable
45:59
across the freeway
46:01
that we have. On
46:04
the Lithuanian side, it
46:07
will be partially cable,
46:09
partially overhead line. Currently,
46:11
the plan is to have
46:13
the new link in 2030. On,
46:17
I think, positive side, both
46:19
we and Lidric, we already
46:21
took the investment decisions and
46:23
we are like, we
46:27
are ready to perform this
46:29
project. The
46:48
engineers we've heard from today
46:50
have dedicated decades of their careers
46:52
to give their countries the
46:54
power to protect freedom's front line.
46:56
The question is, what will
46:59
today's young engineers need to do
47:01
to maintain resilience across Europe's
47:03
infrastructure? Engineering
47:17
Matters is a production of Reby
47:19
Media. This episode was written and
47:21
produced by Will North and edited
47:23
by me, Johnny Dowling. It was
47:25
hosted by me and by Bernadette
47:28
Ballantyne, sound engineering by Ross McPherson.
47:30
And the man who gives us
47:32
the capacity to operate in perfect
47:34
synchronization is Rory Harris. Thank
47:36
you for listening. You can
47:38
find us on all podcast
47:40
apps, on our website, engineeringmatters
47:43
.reby .media, and on LinkedIn. You
Podchaser is the ultimate destination for podcast data, search, and discovery. Learn More